Street Between Street 1 Between Street 2 Milling Date Paving Date
Long Hill Rd Francisco Ave 860' South of Francisco Ave 20-May 28-May
Francisco Ave Greenbriar Ct Long Hill Rd 20-22 May 29-May
Stephen Pl Francisco Ave Long Hill Rd 20-May 28-May
Notch Park Rd Ridge Rd End (East of Ridge Rd) 21-May 28-May
Notchcroft Dr Overlook Ave Long Hill Rd 22,29-May, 30-May
Overlook Ave Hemlock Rd End (East of Hemlock Rd) 22-May 30-May
High Ct Hemlock Rd End (East of Hemlock Rd) 23-May 30-May
Hemlock Rd Crestmont Rd Overlook Ave 23-May 30-May
Crestmont Rd Lower Notch Rd 220' e/o Hemlock Rd 23-May 31-May
Birch Rd Crestmont Rd Overlook Ave 23-24 May 30-May
Overlook Ave Crestmont Rd Birch Rd 24-May 31-May
Lower Notch Rd Long Hill Rd Reg # 140 24, 28 May 31-May, 3-Jun
Sisco Ln Lower Notch Rd End 28-May 3-Jun
Browertown Rd E. Main St RVHS Driveway 29-May 3-Jun
Hudson St 360' E of Randolph Pl End 29-May 4-Jun
Randolph Pl E. Main St Hudson St 29-May 4-Jun
Long Hill Rd West of Jacobus Ave Browertown Rd (Reg # 148) 30-May 4-Jun
Inwood Long Hill Rd End 30-May 4-Jun
Hillcrest Dr Long Hill Rd End 30-May 4-Jun